✅ Definition & Purpose

✅ Key Elements of ITP

✅ Inspection Action Points

  • An inspection point, defined in an appropriate document, beyond which an Activity must not proceed without the approval of the designated organization or authority.
  • An inspection point, defined in an appropriate document, beyond which an Activity can proceed after notifying the designated organization or authority. Contractor’s QC Inspector has the full responsibility for performing detailed Inspection during the work activity.
  • Defined in an appropriate document is the point in which a work activity cannot Proceed without first ensuring the review and approval of applicable documents Or personnel qualification by a designated organization or authority.
  • QA/QC organization to monitor work in progress without notice from construction organization

✅ Inspection Levels as per (SAER – 1972)