Instrument Air Supply QAQC Questionnaires
Instrument Air Supply
4.8 Instrument Air Distribution System
4.8.1 General Requirements
4.8.1.1 Piping material shall be selected in accordance with SAES‐ L‐032. The
selection of alternative piping material requires the approval of the
Coordinator, Mechanical and Civil Engineering Division/CSD.
4.8.1.2 All main and branch headers shall be sloped {minimum 64 mm per 30 m
(2.5 inches per 100 feet)} and provided with low point drains.
4.8.1.3 All headers shall terminate with a line‐size valve, blind, or plug to
facilitate cleaning and plant expansions.
4.8.1.4 Each branch header shall connect to the top of the main header through
a branch‐line‐size, full‐bore isolation valve.
4.8.1.5 Where there is a general distribution system for more than one
plant, the piping shall be connected in a loop to provide two directions of
supply to each plant. Isolation valves shall be provided to enable
isolation of each plant.
4.8.1.6 Supply takeoffs to individual instruments (a line serving up to a maximum
of four devices) shall connect to the top of the branch header through a
takeoff‐line‐size, full‐bore isolation valve.
4.8.1.6.1 The minimum size of supply takeoffs is ½‐inch.
4.8.1.6.2 Twenty percent (20%) spare takeoff fittings and block
valves shall be installed on the branch header.
4.8.1.7 Instrument air piping shall not be pocketed (i.e., shall not contain, Usections).
Instrument air piping shall not be installed underground.
Exception:
Instrument air branch connections may be buried to cross beneath roadways or
fences where there is no existing overhead rack and where the aboveground
support would interfere with crane or emergency vehicle movement. Prior
approval from the General Supervisor, Process Instrumentation Division, P&CSD
is required. Buried branch lines shall have low point drains, stainless steel
construction and external coating per SAES‐H‐002.
4.8.2 Header and Takeoff Sizing
4.8.2.1 The pressure drop for piping between the dryer after filter outlet and the
most remotely located user shall not exceed 35 kPa (5 psi) under
maximum service flow rate.
4.8.2.2 For installations in which the instrument air consumers are located more
than 600 m (2000 ft) from the instrument air compressor; pipe sizes
should be calculated to keep pressure drops within the above limit.
Below 600 m (2000 ft) instrument air header pipe size should be
selected from Table 2. (J‐901)
5 Testing (J-901)
Pressure testing of supply system and distribution system per SAES‐L‐056, using
dry instrument air or inert gas is required. Hydrostatic testing of instrument air
piping is not permitted.
- ARAMCO :: CBT QA/QC – Instrumentation Inspector Qualification Guideline
- Instrumentation Inspection and Quality Control CBT 2021 Questioner – Part-04
- Top 50 Questioner Instrumentation Inspection and Quality Control CBT 2021 – Part-05
- Saudi Aramco Cbt Exam Questions and Answers
- QA/QC Inspector Question & Answer Handbooks-2021
- QA/QC E-books Category
- QAQC Questionnaires CONDUIT; CABLE TRAY; ENCLOSURES;
- QAQC Questionnaires FIELD INSTRUMENT; JUNCTION BOX; COLOR CODING; Grounding (J902)
- Instrument Piping and Tubing QAQC Questionnaires